RACS INDUSTRIAL were contracted to engage and support a major operator within the hydroelectric energy industry. The operator was in the process of overhauling their internal communications network which required specialist access services to undertake the new installation.
Challenges
RACS INDUSTRIAL’s contribution to the project was to install 2 no. fibre optic cables down a 260 meter ventilation shaft via IRATA rope access techniques.
The project involved several key challenges, which were successfully managed throughout delivery:
- The role of the ventilation shaft and associated extractor fans were to provide fire smoke relief to subterranean areas of the power plant. The fans were operated as an on-demand system and could not be 100% isolated in case of a fire emergency. The extractor fans would have to be turned on at some point.
- The sheer depth of the ventilation shaft would result in a prolonged evacuation (or rescue) of persons working at height, within the shaft.
- The working environment within the shaft presented specific challenges including low light levels, high winds and limited communication with team members located outside the shaft.

Solution
The power plant operator’s HSE team were engaging and methodical in their planning and oversight of the task, from the very start.
A task specific set of RAMS and Evacuation & Rescue plan was agreed with the client, with evacuation routes set depending on what height the access team were at within the shaft. Hazard specific PPE and RPE was carried by the accessing team in the event an evacuation due to a fire emergency was required.
A time limit of 7 minutes was set for the accessing team to completely evacuate the shaft before the extractor fans were turned on. The cut of point on whether to ascend of descent the shaft to evacuate was set at 40 meters from the top of the shaft.
Communication methods were established using a combination of ATEX rated 2-way radios between RACS INDUSTRIAL team members and site dedicated land line phones to contact the site control room.
The use of head torches and task lighting aided with the work carried out inside the shaft.

Result
The successful operation of the task was carried out over 4 days on site. Addition time was required at the planning stages and for mobilisation. This was the first project RACS INDUSTRIAL carried out for the client and has not been the last. Further work has included the installation of power cables and confined space entry control.
- The cable installation was completed over four days with no safety concerns, despite difficult shaft conditions.
- RACS delivered the project to a high standard, showcasing professionalism and strong technical capability.
- This successful first project has led to ongoing involvement with the client on further cable and entry control works.