RACS INDUSTRIAL were contracted to undertake the removal of redundant pipework from an area within a chemical manufacturing plant. The removal work was necessary due to the assets presenting an overhead hazard to other contractors on site. The removal work would enable space for future assets to be installed during a future construction project.
Challenges:
The project posed several significant challenges, which were successfully mitigated through careful planning and specialist rope-access techniques:
- The erection of a suitable scaffold structure would have resulted in scaffolders working directly beneath the overhead hazard. In addition to this, the scaffold structure would have caused an obstruction when removing and lowering the pipework to ground level.
- A mobile crane could not be utilised due to the presence of structures and assets above the work areas.
- The manufacturing process that the Caustic pipework was part of meant that the presence of Mercury was highly likely within the pipework, at low points

Solution
Upon productive planning with the client, RACS INDUSTRIAL mobilised an IRATA trained rope access team with various rigging competencies to de-lag and remove all Mercury prior to removing pipework from height, using skilful rigging techniques.
Exclusion zones were established around the work areas at ground level. All RACS INDUSTRIAL personnel were required to wear task specific PPE that prevented exposure to Mercury. In addition to this, occupational health monitoring was carried out prior to, during and after the works were completed.

Result
All pipework was recovered to ground level for the clients site team to decontaminate. The RACS INDUSTRIAL work team were unaffected by exposure to Mercury. The work was completed within the planned timescale for the task which was 5 days on site.
- All redundant pipework was safely recovered to ground level without incident, enabling decontamination by the client’s site team.
- The work was completed within the planned 5-day schedule, with no exposure to Mercury reported among personnel.
- RACS INDUSTRIAL has since been re-engaged by the client for further projects, reflecting high satisfaction with performance and safety standards.